Earthwork on 17th Drive continues. During work hours, 17th Drive northbound traffic will be closed for about 12 days as the underground utility excavation continues. The permits for the patio homes were issued. The demolition of the Garden Apts is progressing quickly. Dust control is in effect at all times. The rubble is being hauled off instead of being utilized as fill. The change in plan is because the noise created during the crushing process was feared to be too loud for Central Park residents. The contractor will still provide the expected credit for the savings for haul off costs, and the contractor will provide the fill at no cost to the Campus. Additional questions and information? Contact Scott Mardian, [email protected]