Beatitudes Community

Redevelopment Update: Sandpainting

We expect the second pour for ready-mix/concrete for the footings and foundations this week or early next week for the second building. The pours will begin at about 3:30AM. Additional notifications will follow when the work schedule is set.

The underground utility work is wrapping up.  The blue piping is for domestic , the black piping is for fire lines, the green piping is for sewer, the gray piping is for electrical and the white piping is for sewer lines inside of the buildings.

We will be working on the east drive/Boutique Blvd. near the dumpsters just north of the next week. There will be restrictions while we tap into the water lines in the roadway.

This week between the hours of 6AM and 3PM from Monday, May 20th—Friday, May 24th the northeast corner of the campus will be CLOSED to DRIVING TRAFFIC due to construction from 6AM to 3PM. PLEASE USE 17TH DRIVE ENTRANCE TO ACCESS THE WEST END OF CAMPUS as you will not be able to drive around.

RESIDENTS, PLEASE NOTE: YOU WILL STILL BE ABLE TO PARK ON THE EAST SIDE OF CAMPUS IN YOUR NORMAL PARKING SPOTS AS ASSIGNED during these times. Security will be directing and notifying those who enter off of Glendale Avenue of these restrictions.

Dust control is in effect at all times on all sites. We appreciate your cooperation and patience during times of construction traffic restrictions. For questions—please contact Scott Mardian, Sr. VP of Redevelopment, [email protected].

Author Info: Beatitudes Campus Verified Administrator
At the foundation of is the vision of Church of the Beatitudes pastors and congregation members to create a better alternative for older adults than the homes of the early 1960s. The type of they imagined was the of its kind in Arizona. Beatitudes Campus is proud to continue the legacy of our founders, by being a leader in the field of services for over 50 years.