We expect the pour of ready-mix/concrete for the floor slabs for building one this Friday, the 31st. The pour for the footings for the second building could be Monday the 3rd or Tuesday the 4th. moving back over to the dirt work for the 17th Drive buildings could begin Wednesday the 5th.
The work in the east drive/Boutique Blvd. near the dumpsters just north of the community garden should wrap up in the middle of this week. There are driving restrictions while we tap into the water lines in the roadway.
Dust control is in effect at all times on all sites.