We are planning to have a second concrete contractor begin working on the 17th Drive site next week. You should see the sitework contractor moving dirt for the building pads this week. The framing will continue on Myrtle with the footings for Bldg #4 being poured on the 14th. The HVAC (Heating, Ventilating, Air Conditioning), will begin installation the week of the 24th on building #5 which was the first pad poured and the building that is framed. The project remains within budget.
Dust control is in effect at all times on all sites.